What if the subfloor is moist or not dry enough?

Make sure that the root cause of the moist subfloor is solved first. Then, you can apply a liquid, damp-proof membrane (liquid DPM). If you want to glue down your vinyl floor, you will need to use a levelling compound, as a porous substrate is required for the glue.

  • The moisture content of the subfloor must be less than 2,5%CM / 75%RH (cement screed) or less than 0,5%CM / 50%RH (anhydrite screed - subfloor).
  • In the case of floor heating, results must be respectively 1,5%CM / 60%RH and 0,3%CM / 40%RH.

Always measure, record and keep your moisture content results.

A new cement screed floor must dry at least 1 week per 1cm (3/8”) thickness up to 4cm (1-1/2”). Thicknesses over 4cm (1-1/2”) require twice as much drying time. For example, a 6 cm (2-1/2”) concrete subfloor must dry at least 8 weeks.

Was this article helpful?
How can we improve this article?

Thank you for your feedback!

Oops. Something went wrong.

An unknown error has occurred. Please try again. If the issue continues, please get in touch.